Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ban-users domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/u382405524/domains/xlprojects.net/public_html/staging/wp-includes/functions.php on line 6131

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the heartbeat-control domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/u382405524/domains/xlprojects.net/public_html/staging/wp-includes/functions.php on line 6131
SaCeMa Nordic Projects and Rohlig Suus Logistics Collaborate to Relocate One of the Biggest Paper Making Machines in the World – XLP Projects Network
loader image
News

SaCeMa Nordic Projects and Rohlig Suus Logistics Collaborate to Relocate One of the Biggest Paper Making Machines in the World

2 min read

SaCeMa Nordic Projects, XLP Member in Denmark, answered the phone call in April and got immediately awarded to relocate “One of the biggest paper making machines in the world, within 8 months”

Predicted contract by customer

Sweden – Poland

1 paper making machine 350 meters x 12 meters x 19 meters / about 8000 ton

300 x trucks IG and OOG up to 1,900 x 350 x 380 cms and up to 108 ton units + 30 x 40’HC SOC.

Started 2 May 2022, Deadline 22 December 2022

SaCeMa Nordic Projects teamed up with fellow XLP Member, Rohlig Suus in Poland, who quickly understood the need, to fulfill commitment, against the customer.

Final Result

Sweden – Poland

1 paper making machine 350 meters x 12 meters x 19 meters / about 8000 ton

480 x trucks IG and OOG up to 1,900 x 350 x 380 cms and up to 108 ton units + 38 x 40’ HC SOC.

Started 2 May 2022, SaCeMa Nordic Projects, finalized 15 December 2022

The project was successfully completed in 7.5 months. Thank you, our great partner Rohlig Suus. The building was handed over to the battery company on 22 December for new adventures.

 

SaCeMa Nordic Projects “The Best Never Rest”

” Denmark – Sweden – Finland – Norway “

Recent Post
Rack Shipment
Manuport Logistics Greece and Round Logistics Drive Successful OOG Flat Rack Shipment Through XLP Collaboration
News
XLProjects Network (XLP)
Tianjin-to-Libya Shipment Demonstrates Heavy Project Cargo Capability by Xiamen Rosen Shipping
News
W.T.I (Cambodia) Co., Ltd. in Phnom Penh, Cambodia joins XLProjects Network (XLP)
News

Ready to become a member? Let’s work together

Contact our AiO Logistics Team who will be happy to talk to you!